Getting there

I ordered my cabin last week, which means the shell should get delivered by the end of October, so the real work begins in earnest.

I cut the grass finally, so the next step is to stake out where the house will go. Weather and stomach issues have delayed that part, but I hope to do it after work in the coming week and pull the septic permit as soon as possible.

I met with the loan officer on Saturday and there are a few possibilities, which will all get resolved in the next week or two.

Once the septic tank is installed, I can have the foundation installed. Once the shell is delivered, I will get the electrical and plumbing work done, then the builder will come out and insulate and finish the interior walls and ceiling while I get the rain gutters and cistern installed and the water system up and running.

After that comes the laminated wood flooring, kitchen and bathroom cabinets, light fixtures, shower, toilet and appliances (stove, refrigerator and dishwasher.) Yes, a dishwasher. They use less water than if I did the dishes by hand.

If everything works out (which it usually does) I’ll be in my new home before Christmas.

Estimated cost, less than $65,000, including the land.

Here’s a peek at what the inside of the cabin will look like.

Read Full Post »